top of page
BB-construction logo_PMS_edited.png

Weekly Project Update

St. Louis Catholic Church Office Addition

Placeholder

THIS WEEK'S ACCOMPLISHMENT

    Select fill and testing completed at the building pad
    Pond excavation continues
    Eagle Eye was out and set the building corners and gridlines
    Axis concrete delivered equipment and started excavating Friday
    JM Utilities received the permit and will start fire line again Monday
    Kinney's started excavating for waste water line tie in.
Excavation 1.jpg

Pond excavation in progress

NEXT WEEK'S ACTIVITIES

    Axis Concrete continues excavating grade beams at slab
    JR Schneider Continue removing spoils at pond (should be completed this week)
    JM Utilities will continue fire line and inspections
    Kinney's will start excavating for wastewater lines at the pad and tying into the existing
Excavation 1.jpg

Pad completed and at elevation

Excavation 1.jpg

Axis started excavating grade beams

LOOK AHEAD SCHEDULE

Click on document icon below to review the detailed Look Ahead Schedule.

bottom of page