Weekly Project Update
St. Louis Catholic Church Office Addition
THIS WEEK'S ACCOMPLISHMENT
- Select fill and testing completed at the building pad
- Pond excavation continues
- Eagle Eye was out and set the building corners and gridlines
- Axis concrete delivered equipment and started excavating Friday
- JM Utilities received the permit and will start fire line again Monday
- Kinney's started excavating for waste water line tie in.

Pond excavation in progress
NEXT WEEK'S ACTIVITIES
- Axis Concrete continues excavating grade beams at slab
- JR Schneider Continue removing spoils at pond (should be completed this week)
- JM Utilities will continue fire line and inspections
- Kinney's will start excavating for wastewater lines at the pad and tying into the existing
-

-
Pad completed and at elevation

Axis started excavating grade beams
LOOK AHEAD SCHEDULE
Click on document icon below to review the detailed Look Ahead Schedule.