Weekly Project Update

San Juan Diego Catholic School

Placeholder

Martin Diaz

THIS WEEK'S ACCOMPLISHMENT

    Complete the install of the facia and gutters at the gym
    Complete the install of the facia and gutter at the lower roof
    complete the install of the facia and gutter at the main entrance tower
    complete the front side of the 2nd story facia and gutter work
    started the gym masking at the gym
Excavation 1.jpg

start masking on the inside gym walls and fixtures. Prep for the painting of the ceiling

NEXT WEEK'S ACTIVITIES

    Complete the back side of the 2nd story building facia work and install of gutter
    Roof metal panels arrive to the San Juan Diego catholic school site
    Start install metal clips on the gym room.
    Load Metal roof panels on the gym roof
    Start the install of the roof panels at the gym
Excavation 1.jpg

Facia and Gutter install ongoing

Excavation 1.jpg

Moved lift to the front to complete the facia and gutter work while school is out.

LOOK AHEAD SCHEDULE

Click on document icon below to review the detailed Look Ahead Schedule.