THIS WEEK'S ACCOMPLISHMENT
- Complete the install of the facia and gutters at the gym
- Complete the install of the facia and gutter at the lower roof
- complete the install of the facia and gutter at the main entrance tower
- complete the front side of the 2nd story facia and gutter work
- started the gym masking at the gym
-

start masking on the inside gym walls and fixtures. Prep for the painting of the ceiling
NEXT WEEK'S ACTIVITIES
- Complete the back side of the 2nd story building facia work and install of gutter
- Roof metal panels arrive to the San Juan Diego catholic school site
- Start install metal clips on the gym room.
- Load Metal roof panels on the gym roof
- Start the install of the roof panels at the gym

-
Facia and Gutter install ongoing

Moved lift to the front to complete the facia and gutter work while school is out.