top of page


Weekly Project Update
San Juan Diego Catholic School

Martin Diaz
THIS WEEK'S ACCOMPLISHMENT
- Gym roof complete install of roof panels and trim work. Soffit remains
- 2nd story Building roof panels complete
- 2nd story trim work in process
- Soffit work on the 2nd story has started
- Approve paint colors to paint the stained stucco exterior walls
-

Gym roof and trim complete
NEXT WEEK'S ACTIVITIES
- work on the lower roof. Install the remaining roof panels
- start the trim work on the entire roof
- Paint stucco on the front side of the school, only.
-
-

-
2nd story building roof complete

The trim work on 2nd story building has started
LOOK AHEAD SCHEDULE
Click on document icon below to review the detailed Look Ahead Schedule.
bottom of page