Weekly Project Update
PFISD SAFETY & SECURITY UPGRADES PHASE 3

Dakota Zimmerman
THIS WEEK'S ACCOMPLISHMENT
- Finished installing new Security Doors & Hardware at Hendrickson HS
- Installed new Security Doors & Hardware at Connelly HS
- Installed Mag holds at new Security Doors at Hendrickson HS.
- Programed new Card Readers & Lockdown button at Admin Bldg.
-
-

Installing new Security Doors & Hardware at Connelly HS. (AA8)
NEXT WEEK'S ACTIVITIES
- Finish Installing new Security Doors & Hardware at Connelly HS.
- Install Mag Holds at Kelly Lane MS Storefront
- Field test new Lockdown Button at Dessau, Kelly Lane, Park Crest, Westview MS, & Hendrickson HS.
-
-

-
Programming new Card Readers & Lockdown at Admin Bldg.

Installing new Security Doors & Hardware at Connelly HS. (AA3)
LOOK AHEAD SCHEDULE
Click on document icon below to review the detailed Look Ahead Schedule.