Weekly Project Update

PFISD SAFETY & SECURITY UPGRADES PHASE 3

Placeholder

Dakota Zimmerman

THIS WEEK'S ACCOMPLISHMENT

    Continued Tape, Float, Texture & Paint at Connelly HS.
    Verified all ACP's are wired up, labeled, and ready for programming.
    Site walked Cele MS with PFISD to come up with final design.
Excavation 1.jpg

Wired up ACP ready for Programming at Westview MS

NEXT WEEK'S ACTIVITIES

    Start programming at all Phase 3 Schools. (Excluding Admin Bldg)
    Install Cove Base at Hendrickson HS.
    Repair flooring from Locker Demo & classroom re-locations at Connelly HS. (2nd Floor)
    Repair Flooring from Classroom Door relocation at Provan Opportunity Center.
    Continue Tape, Float, Texture & Paint at Connelly HS.
Excavation 1.jpg

Spraying texture at Connelly HS

Excavation 1.jpg

Wired up ACP ready for Programming at Connelly HS (2nd Floor)

LOOK AHEAD SCHEDULE

Click on document icon below to review the detailed Look Ahead Schedule.