THIS WEEK'S ACCOMPLISHMENT
- Pulled cable for the AI-Phone at the Admin Bldg, Cele Middle School, Kelly Lane Middle School, & Park Crest Middle School. (Cable pull complete)
- Finished installing HM Door Frames at Kelly Lane Middle School.
- Started installing HM Door Frames at Hendrickson High School.
- Tape, Floated, Textured & Painted at Dessau Middle School.
- Installed Steel Beam for Storefront W9, and Finished building Box Beam header for Storefront W11 at Kelly Lane Middle School.
-

Painting at Dessau Middle School.
NEXT WEEK'S ACTIVITIES
- Continue installing HM Door Frames at Hendrickson High School.
- Install pathways for AI-Phone at all 9 Phase 3 School's, & start Installing AI-Phones at Phase 3 School's.
- Finish Tape, Float, Texture & Paint at Dessau, & Westview Middle School.
- Field Measure new Storefront at Kelly Lane Middle School.
- Field Measure Sliding Glass Windows and Transom Glass at Dessau MS, Cele MS, Provan Oppurtunity Center, Park Crest MS, Kelly Lane MS, Pflugerville MS, Westview MS, Connelly HS, Hendrickson HS.

- Install Cove Base & Signage at Pflugerville MS, Dessau MS, Park Crest MS, & Westview MS.
Installing HM Door Frames at Hendrickson High School.

Installing Steel Beam for Storefront at Kelly Lane Middle School.