Weekly Project Update

PFISD SAFETY & SECURITY UPGRADES PHASE 2 & 3

Placeholder

Dakota Zimmerman

THIS WEEK'S ACCOMPLISHMENT

    Installed AI-Phone at Connelly HS & Dessau MS.
    Finished Tape, Float, Texture & Paint at Kelly Lane MS.
    Finished Installing HM Door Frames at Hendrickson HS. (2nd Floor)
    Started Tape & Floating at Hendrickson HS. (2nd Floor)
Excavation 1.jpg

Installed AI-Phone at Connelly HS

NEXT WEEK'S ACTIVITIES

    Install AI-Phone at Westview MS.
    Program Card Reader at Parmer Lane Elementary.
    Continue Tape & Float at Hendrickson HS. (2nd Floor)
    Re-Locating Light Switches at Connelly HS for HM Frame install.
    Install Deal Tray & Notched Glass at Hendrickson HS.
Excavation 1.jpg
    Install Cove Base at Westview MS, Dessau MS, Pflugerville MS, & Park Crest MS.

Painting at Kelly Lane MS

Excavation 1.jpg

Installed HM Door Frame at Hendrickson HS.

LOOK AHEAD SCHEDULE

Click on document icon below to review the detailed Look Ahead Schedule.