Northwest ES Renovations 6/21/2024
Michael Olmos
THIS WEEK'S ACCOMPLISHMENT
- Extended urinal connections in restroom A to account for new tile thickness
- Extended urinal connections in restroom B to account for new tile thickness
- Extended urinal connections in restroom C to account for new tile thickness
- Installed new floor drains and cleanouts in restrooms
- Poured back concrete around new floor drains and cleanouts
- New floor tile, mortar, thinset, and grout delivered
Restroom B boys urinal connections extended
NEXT WEEK'S ACTIVITIES
- Float floor in restroom set A
- Float floor in restroom set B
- Float floor in restroom set C
- Start floor tile installation in restroom set A
- Start floor tile installation in restroom set B
- Start floor tile installation in restroom set C
Tile material delivered (floor tile, grout, thinset, mortar)
Restroom C girls floor drain and cleanout installed
LOOK AHEAD SCHEDULE
Click on document icon below to review the detailed Look Ahead Schedule.