top of page
BB-construction logo_PMS_edited.png

Weekly Project Update

Northwest ES Renovations 6/21/2024

Placeholder

Michael Olmos

THIS WEEK'S ACCOMPLISHMENT

    Extended urinal connections in restroom A to account for new tile thickness
    Extended urinal connections in restroom B to account for new tile thickness
    Extended urinal connections in restroom C to account for new tile thickness
    Installed new floor drains and cleanouts in restrooms
    Poured back concrete around new floor drains and cleanouts
    New floor tile, mortar, thinset, and grout delivered
Excavation 1.jpg

Restroom B boys urinal connections extended

NEXT WEEK'S ACTIVITIES

    Float floor in restroom set A
    Float floor in restroom set B
    Float floor in restroom set C
    Start floor tile installation in restroom set A
    Start floor tile installation in restroom set B
Excavation 1.jpg
    Start floor tile installation in restroom set C

Tile material delivered (floor tile, grout, thinset, mortar)

Excavation 1.jpg

Restroom C girls floor drain and cleanout installed

LOOK AHEAD SCHEDULE

Click on document icon below to review the detailed Look Ahead Schedule.

bottom of page