top of page


Weekly Project Update
Murchison Elementary 6-28-24

Keith Farrell
THIS WEEK'S ACCOMPLISHMENT
- Completed flooring in upstairs corridor in area C
- Prepped both corridors for flooring installation
- Completed ceramic tile in east stairwell
- Started ceramic tile in lower level ramp
- Completed first coat of paint in area B & D
- Received tack board material

Completed wainscot in stairwell
NEXT WEEK'S ACTIVITIES
- Prep classrooms in B & D areas for flooring installation
- Finish ceramic tile on ramp walls
- Lay flooring in entry vestibule
- Start tile wainscot in main corridor
- Lay flooring in first floor corridor

- Patch, prep, and paint tack board and white board areas
Tile wainscot on lower ramp

Second floor corridor prepped for flooring installation
LOOK AHEAD SCHEDULE
Click on document icon below to review the detailed Look Ahead Schedule.
bottom of page