Weekly Project Update

Murchison Elementary 6-28-24

Placeholder

Keith Farrell

THIS WEEK'S ACCOMPLISHMENT

    Completed flooring in upstairs corridor in area C
    Prepped both corridors for flooring installation
    Completed ceramic tile in east stairwell
    Started ceramic tile in lower level ramp
    Completed first coat of paint in area B & D
    Received tack board material
Excavation 1.jpg

Completed wainscot in stairwell

NEXT WEEK'S ACTIVITIES

    Prep classrooms in B & D areas for flooring installation
    Finish ceramic tile on ramp walls
    Lay flooring in entry vestibule
    Start tile wainscot in main corridor
    Lay flooring in first floor corridor
Excavation 1.jpg
    Patch, prep, and paint tack board and white board areas

Tile wainscot on lower ramp

Excavation 1.jpg

Second floor corridor prepped for flooring installation

LOOK AHEAD SCHEDULE

Click on document icon below to review the detailed Look Ahead Schedule.