Weekly Project Update
Integral Care
Martin Diaz
THIS WEEK'S ACCOMPLISHMENT
- Room 306 Hook up Cassette unit with refrigerator lines and powered up the outside unit complete.
- Tape and float of all 3 floor fur downs complete
- Strayed texture on ceiling 206
- Strayed texture in all 3rd floor rooms and painted.
- Integral care flooring company delivered a dumpster, but no show.
-
Refrigerator lines and power hooked up. Waiting for start up. Call for Mechanical final
NEXT WEEK'S ACTIVITIES
- Start up for AC cassette in room 306
- Call for Mechanical final for the 3rd floor
- Frame fur down in room 306
- Complete change order repair of the Existing fire alarm so we can call for a fire final.
- Complete Spraying Texture in the 2nd floor and Paint
- Complete spraying texture in the 1st floor
Sprayed Texture finish in room 206 and Fur downs on 3rd floor
Spraying texture and painting 3rd floor fur downs
LOOK AHEAD SCHEDULE
Click on document icon below to review the detailed Look Ahead Schedule.