Weekly Project Update

Integral Care

Placeholder

Martin Diaz

THIS WEEK'S ACCOMPLISHMENT

    Room 306 Hook up Cassette unit with refrigerator lines and powered up the outside unit complete.
    Tape and float of all 3 floor fur downs complete
    Strayed texture on ceiling 206
    Strayed texture in all 3rd floor rooms and painted.
    Integral care flooring company delivered a dumpster, but no show.
Excavation 1.jpg

Refrigerator lines and power hooked up. Waiting for start up. Call for Mechanical final

NEXT WEEK'S ACTIVITIES

    Start up for AC cassette in room 306
    Call for Mechanical final for the 3rd floor
    Frame fur down in room 306
    Complete change order repair of the Existing fire alarm so we can call for a fire final.
    Complete Spraying Texture in the 2nd floor and Paint
Excavation 1.jpg
    Complete spraying texture in the 1st floor

Sprayed Texture finish in room 206 and Fur downs on 3rd floor

Excavation 1.jpg

Spraying texture and painting 3rd floor fur downs

LOOK AHEAD SCHEDULE

Click on document icon below to review the detailed Look Ahead Schedule.