Weekly Project Update

Integral Care

Placeholder

Martin Diaz

THIS WEEK'S ACCOMPLISHMENT

    Completed all Millwork installation for all 3 floors
    Painting all rooms in the 3rd floor minus the wall where the new millwork was installed. Awaiting furdown
    Installed Duct work for the for the vent hood
    All the hoods on all 3 floors are installed
    LVL for room 206 ceiling to help brace 306 floor is installed
    Painter is priming all rooms in the 2nd floor to start painting.
Excavation 1.jpg

Duct work has started and Hood is installed on each room where new millwork is installed

NEXT WEEK'S ACTIVITIES

    Complete painting of 2nd floor rooms and move to the first floor
    All duct work for all 3 floors will be complete and inspected
    Frame fur downs to hide the duct work and painter will start to tape and float
    Counter tops installation will start if a decision the sink is made. Counter top are ready for 2 floors minus the sink
    Ceiling for room 206 will be covered up.
Excavation 1.jpg

All 3 floors of millwork, and shelves are installed. awaiting countertop.

Excavation 1.jpg

LVL in room 206 is installed. Will wait a week before installing ceiling

LOOK AHEAD SCHEDULE

Click on document icon below to review the detailed Look Ahead Schedule.