Weekly Project Update
Integral Care

Martin Diaz
THIS WEEK'S ACCOMPLISHMENT
- Completed all Millwork installation for all 3 floors
- Painting all rooms in the 3rd floor minus the wall where the new millwork was installed. Awaiting furdown
- Installed Duct work for the for the vent hood
- All the hoods on all 3 floors are installed
- LVL for room 206 ceiling to help brace 306 floor is installed
- Painter is priming all rooms in the 2nd floor to start painting.

Duct work has started and Hood is installed on each room where new millwork is installed
NEXT WEEK'S ACTIVITIES
- Complete painting of 2nd floor rooms and move to the first floor
- All duct work for all 3 floors will be complete and inspected
- Frame fur downs to hide the duct work and painter will start to tape and float
- Counter tops installation will start if a decision the sink is made. Counter top are ready for 2 floors minus the sink
- Ceiling for room 206 will be covered up.

-
All 3 floors of millwork, and shelves are installed. awaiting countertop.

LVL in room 206 is installed. Will wait a week before installing ceiling
LOOK AHEAD SCHEDULE
Click on document icon below to review the detailed Look Ahead Schedule.