Weekly Project Update

Hyde Park Field House

Placeholder

Nathan Stanford

THIS WEEK'S ACCOMPLISHMENT

    Poured more retaining walls and brick lugs
    Staged all material on roof in anticipation of start roof work to get dried in.
    Sidewalks, monument sign, screen wall footing formed for pouring next week.
    Mechanical, Electrical, & Plumbing (MEP) continue to rough in walls.
    Screw inspection for exterior sheathing passed and waterproofing started.
    Primer and first coat of paint on remodel area.
Excavation 1.jpg

Roof stockpiled for getting started soon.

NEXT WEEK'S ACTIVITIES

    Pour more sidewalks.
    Backfill retaining wall with drains
    Continue rough in of walls
    Roofing starts with anticipation of getting dried in by end of the week.
    Some metal doors on exterior start to install so they can paint first coat along with door frames paint.
Excavation 1.jpg
    Start blue rigid insulation on outside of building.

95% of interior walls studs standing for MEP trades to rough in

Excavation 1.jpg

Exterior wall sheathing complete. Waterproofing has started.

LOOK AHEAD SCHEDULE

Click on document icon below to review the detailed Look Ahead Schedule.

bottom of page