top of page


Weekly Project Update
Hyde Park Field House

Nathan Stanford
THIS WEEK'S ACCOMPLISHMENT
- Poured more retaining walls and brick lugs
- Staged all material on roof in anticipation of start roof work to get dried in.
- Sidewalks, monument sign, screen wall footing formed for pouring next week.
- Mechanical, Electrical, & Plumbing (MEP) continue to rough in walls.
- Screw inspection for exterior sheathing passed and waterproofing started.
- Primer and first coat of paint on remodel area.

Roof stockpiled for getting started soon.
NEXT WEEK'S ACTIVITIES
- Pour more sidewalks.
- Backfill retaining wall with drains
- Continue rough in of walls
- Roofing starts with anticipation of getting dried in by end of the week.
- Some metal doors on exterior start to install so they can paint first coat along with door frames paint.

- Start blue rigid insulation on outside of building.
95% of interior walls studs standing for MEP trades to rough in

Exterior wall sheathing complete. Waterproofing has started.
LOOK AHEAD SCHEDULE
Click on document icon below to review the detailed Look Ahead Schedule.
bottom of page