THIS WEEK'S ACCOMPLISHMENT

    Getting pad ready to pour next week
    Started Insulation on interior walls
    Started one side sheet rock to hold up insulation
    Rough in ceilings continue electrical
    Rough in ceilings continue mechanical
    Rough in pad for plumber pre-pour drains and showers
Excavation 1.jpg

Sheet rock has started on the walls one side to hold up insulation

NEXT WEEK'S ACTIVITIES

    Pour slab
    Steel arrives and unloads
    Rough in above ceilings continue Mechanical and electrical
    Insulation of walls continues.
    One side of sheet rock continues
Excavation 1.jpg
    Start forms on sidewalk at the rear planned, but not confirmed.

Insulation of walls has started

Excavation 1.jpg

Pad re-bar 99% getting ready for pour next week.