Weekly Project Update
Hyde Park Field House

Nathan Stanford
THIS WEEK'S ACCOMPLISHMENT
- Getting pad ready to pour next week
- Started Insulation on interior walls
- Started one side sheet rock to hold up insulation
- Rough in ceilings continue electrical
- Rough in ceilings continue mechanical
- Rough in pad for plumber pre-pour drains and showers

Sheet rock has started on the walls one side to hold up insulation
NEXT WEEK'S ACTIVITIES
- Pour slab
- Steel arrives and unloads
- Rough in above ceilings continue Mechanical and electrical
- Insulation of walls continues.
- One side of sheet rock continues

- Start forms on sidewalk at the rear planned, but not confirmed.
Insulation of walls has started

Pad re-bar 99% getting ready for pour next week.
LOOK AHEAD SCHEDULE
Click on document icon below to review the detailed Look Ahead Schedule.