Weekly Project Update

Hyde Park Field House

Placeholder

Nathan Stanford

THIS WEEK'S ACCOMPLISHMENT

    Roof dried in, except for awning at front door
    Mechanical work continues to install
    Electrical work continues to installl
    Plumbing work continues to install
    95% of sidewalks formed to pour next week
    Remodel area 1st coat of paint complete. Ceiling grid started.
Excavation 1.jpg

Outside of building waterproofed and ready for rigid insulation

NEXT WEEK'S ACTIVITIES

    Crane air conditioning units up to roof.
    Pour most sidewalks
    Mechanical work (rough in) continues inside and on roof
    Electrical work (rough in) continues inside and on roof
    Remodel area ceiling grid work continues mechanical and electrical
Excavation 1.jpg
    Plumbing work (rough in) continues inside new addition.

Duct hanging in new addition and MEP roughing in walls

Excavation 1.jpg

Roof dried in and finishing walk pads

LOOK AHEAD SCHEDULE

Click on document icon below to review the detailed Look Ahead Schedule.