top of page


Weekly Project Update
Hyde Park Field House

Nathan Stanford
THIS WEEK'S ACCOMPLISHMENT
- Roof dried in, except for awning at front door
- Mechanical work continues to install
- Electrical work continues to installl
- Plumbing work continues to install
- 95% of sidewalks formed to pour next week
- Remodel area 1st coat of paint complete. Ceiling grid started.

Outside of building waterproofed and ready for rigid insulation
NEXT WEEK'S ACTIVITIES
- Crane air conditioning units up to roof.
- Pour most sidewalks
- Mechanical work (rough in) continues inside and on roof
- Electrical work (rough in) continues inside and on roof
- Remodel area ceiling grid work continues mechanical and electrical

- Plumbing work (rough in) continues inside new addition.
Duct hanging in new addition and MEP roughing in walls

Roof dried in and finishing walk pads
LOOK AHEAD SCHEDULE
Click on document icon below to review the detailed Look Ahead Schedule.
bottom of page