Weekly Project Update

Hyde Park Field House

Placeholder

Nathan Stanford

THIS WEEK'S ACCOMPLISHMENT

    Cabinets arrived and started to install
    Plumbing Fixtures starting to install
    Flooring starting to install
    Landscaping on hold
    Mechanical inspections on hold
    Ice machines set for school use
Excavation 1.jpg

Electrical new panels completing ready for Austin Energy next week

NEXT WEEK'S ACTIVITIES

    Austin Energy powers up new building
    All cabinets should be completed including school changes
    Flooring continues
    Some final trade inspections scheudle.
    Most toilet accessories install
Excavation 1.jpg
    Finish work in occupied school locker rooms over Christmas break.

Air Conditioning units set waiting on Austin Energy next week

Excavation 1.jpg

Ballistic front doors and windows arrived and are getting installed

LOOK AHEAD SCHEDULE

Click on document icon below to review the detailed Look Ahead Schedule.

bottom of page