Weekly Project Update
Hyde Park Field House

Nathan Stanford
THIS WEEK'S ACCOMPLISHMENT
- Cabinets arrived and started to install
- Plumbing Fixtures starting to install
- Flooring starting to install
- Landscaping on hold
- Mechanical inspections on hold
- Ice machines set for school use

Electrical new panels completing ready for Austin Energy next week
NEXT WEEK'S ACTIVITIES
- Austin Energy powers up new building
- All cabinets should be completed including school changes
- Flooring continues
- Some final trade inspections scheudle.
- Most toilet accessories install

- Finish work in occupied school locker rooms over Christmas break.
Air Conditioning units set waiting on Austin Energy next week

Ballistic front doors and windows arrived and are getting installed
LOOK AHEAD SCHEDULE
Click on document icon below to review the detailed Look Ahead Schedule.