Weekly Project Update
Hyde Park Field House

Nathan Stanford
THIS WEEK'S ACCOMPLISHMENT
- Started paint on new addition inside
- Cleaned up outside so irrigation can start next week
- All stone work 99%. Waiting on some caps on half walls
- Above ceiling inspection in new rest rooms so sheet rock could continue
- Wood deck on outside completed
- Metal coping on roof parapet continues. 75% complete. All TPO roof 100%

Ceramic tile started in remodel area.
NEXT WEEK'S ACTIVITIES
- Ceiling Grid starts on new addition
- Lights and A/C grilles install in new grid
- Irrigation starts
- Pulling wires for main electrical gear to happen.
- More ceramic tile continues

- Some flooring upstairs starts
Front stone work completed.

Wood deck completed. Site graded ready for irrigation.
LOOK AHEAD SCHEDULE
Click on document icon below to review the detailed Look Ahead Schedule.