Weekly Project Update

Hyde Park Field House

Placeholder

Nathan Stanford

THIS WEEK'S ACCOMPLISHMENT

    Started paint on new addition inside
    Cleaned up outside so irrigation can start next week
    All stone work 99%. Waiting on some caps on half walls
    Above ceiling inspection in new rest rooms so sheet rock could continue
    Wood deck on outside completed
    Metal coping on roof parapet continues. 75% complete. All TPO roof 100%
Excavation 1.jpg

Ceramic tile started in remodel area.

NEXT WEEK'S ACTIVITIES

    Ceiling Grid starts on new addition
    Lights and A/C grilles install in new grid
    Irrigation starts
    Pulling wires for main electrical gear to happen.
    More ceramic tile continues
Excavation 1.jpg
    Some flooring upstairs starts

Front stone work completed.

Excavation 1.jpg

Wood deck completed. Site graded ready for irrigation.

LOOK AHEAD SCHEDULE

Click on document icon below to review the detailed Look Ahead Schedule.