top of page
BB-construction logo_PMS_edited.png

Weekly Project Update

Hyde Park Field House

Placeholder

Richard Huddleston

THIS WEEK'S ACCOMPLISHMENT

    Passed insulation inspection
    Started stone work
    Last of duct arrived and installed
    Rough in above ceiling plumbing and electrical
    Minis split condenser set and piping started
    Gas piping on roof
Excavation 1.jpg

Insulation inspection passed

NEXT WEEK'S ACTIVITIES

    Sheet rock continues
    Masonry continues
    Insulation on water pipes starts
    Above grid work on remodel area should complete
    School's security contractor should get door swipes going???
Excavation 1.jpg
    Concrete staging area to clean up.

Sheet rock walls has started

Excavation 1.jpg

Stone work has started

LOOK AHEAD SCHEDULE

Click on document icon below to review the detailed Look Ahead Schedule.