THIS WEEK'S ACCOMPLISHMENT

    Steel finishes erection
    Pour some flatwork sidewalks at rear of building
    Siding and associated trim start on storage walls.
    Plywood on interior of storage walls started.
    Sheet rock continues on inside remodel part.
    Repairs to existing building skin 75% complete.
Excavation 1.jpg

Concrete flatwork (sidewalks) has started. Will continue for 3 weeks +/-

NEXT WEEK'S ACTIVITIES

    Form more flatwork concrete sidewalks
    Sheet rock on remodel area should wrap up.
    Plywood on large storage room interiors should wrap up.
    Framing for hard (sheet rock) ceiling should start
    Metal suds on new addition to start.
Excavation 1.jpg
    Over head doors in rear should install

Esterior walls waterproofed, insulated, trimmed and ready for siding panels.

Excavation 1.jpg

Steel columns, beams, joist installed and welded in place.