THIS WEEK'S ACCOMPLISHMENT
- Steel finishes erection
- Pour some flatwork sidewalks at rear of building
- Siding and associated trim start on storage walls.
- Plywood on interior of storage walls started.
- Sheet rock continues on inside remodel part.
- Repairs to existing building skin 75% complete.

Concrete flatwork (sidewalks) has started. Will continue for 3 weeks +/-
NEXT WEEK'S ACTIVITIES
- Form more flatwork concrete sidewalks
- Sheet rock on remodel area should wrap up.
- Plywood on large storage room interiors should wrap up.
- Framing for hard (sheet rock) ceiling should start
- Metal suds on new addition to start.

- Over head doors in rear should install
Esterior walls waterproofed, insulated, trimmed and ready for siding panels.

Steel columns, beams, joist installed and welded in place.
LOOK AHEAD SCHEDULE