THIS WEEK'S ACCOMPLISHMENT
- Finished compaction and filling of building pad
- Blue topped Storm Pond 2 and Building Pad
- Finished relocation of existing propane tank and storage shed
- Finished removal of tree in the front to make way for the new driveway
-
-

Storm Pond 2 blue topped
NEXT WEEK'S ACTIVITIES
- Complete layout of building corners and offsets
- Start formwork for slab on grade
- Perform form survey
- Start plumbing underslab rough in
- Start electrical underslab rough in

-
Existing tree and CMU wall removed, existing propane tank relocated

Building Pad complete and blue topped
LOOK AHEAD SCHEDULE
Click on document icon below to review the detailed Look Ahead Schedule.