Weekly Project Update
Griffith and Paseo

Ian Doyle
THIS WEEK'S ACCOMPLISHMENT
- Finished Installing Roof B
- Continued HVAC Rough In
- Continued Installing Storm Water on West Side
- Continued Electrical Rough In Level 2
- Started Installing Roof A
-

Roof A Installation
NEXT WEEK'S ACTIVITIES
- Finish Installing Roof A
- Finish Installing Storm Water on West Side
- Continue HVAC Rough In
- Continue Electrical Rough In
- Continue Plumbing Rough In

-
Storm Water Manhole Installation

Roof Parapet Steel Installation
LOOK AHEAD SCHEDULE
Click on document icon below to review the detailed Look Ahead Schedule.