THIS WEEK'S ACCOMPLISHMENT
- Finished Installing SE Crawl Space Sanitary Sewer Lines
- Finished Connecting to Exterior Sanitary Sewer Line
- Continued Mechanical, Electrical and Plumbing Rough In
- Continued Framing and Exterior Sheathing
- Started Installing HVAC Ductwork Insulation
-

South Balcony Structural Steel Reinforcement
NEXT WEEK'S ACTIVITIES
- Finish Pouring Concrete for Elevator Pit Walls
- Finish Pouring Concrete for Floor Infills
- Finish Drilling and Pouring Concrete for Exterior Piers
- Continue Mechanical, Electrical and Plumbing Rough In
- Start Installing Structural Shoring for Visitor Center

-
Fire Sprinkler Rough In

Installation of Audio Visual Back Boxes