THIS WEEK'S ACCOMPLISHMENT
- Finished Demolition of Concrete Block Wall on East Side
- Finished Demolition of Dumpster Enclosures on West Side
- Finished Cutting Topping Slab for South Porch Area
- Continued Laying Out / Installing Ductwork Level 1
- Continued Laying Out / Installing Conduit Level 1 & 2
- Started Demolition of Concrete Block Wall South Side
Cutting of Topping Slab in South Porch Area Completed
NEXT WEEK'S ACTIVITIES
- Finish Demolition of Concrete Block Wall South Side
- Finish Cutting Elevator Floor Openings Level 1 and 2
- Finish Laying Out / Installing Ductwork Level 1
- Continue Laying Out / Installing Conduit Level 1 & 2
- Start Laying Out / Installing Ductwork Level 2
-
Demolition of Concrete Block Wall Completed on East Side
Demolition of Concrete Block Wall Completed on West Side
LOOK AHEAD SCHEDULE
Click on document icon below to review the detailed Look Ahead Schedule.