Weekly Project Update

FUMC

Placeholder

Pat Tims

THIS WEEK'S ACCOMPLISHMENT

    Dome is completed
    Fire Alarm Installation Nearing Completion
    Stanton Studios Continues Sanctuary Window Restoration
    Pyramid Casting Cornice Stones For The East Elevation
    Removed Plywood Panels At The Southwest Elevation For Increased Visibility At The Access Ramp
    Laydown Yard Storage Increased With Move Of Finials To East Elevation Garden
Excavation 1.jpg

Dome With Batten Strips

NEXT WEEK'S ACTIVITIES

    Stanton Studios Installation Of Sanctuary Windows S-402 & S-404
    Fire Alarm Completed & Scheduled For Inspection
    Pyramid Stone #4 Cornice Stone Delivery Of 8 Stones
    Red River Restoration Fabricating New Trim For Sanctuary Windows
    Stanton Studios Removal Of Two Additional Windows For Restoration
Excavation 1.jpg
    Presidio Metalworks Updates On Guardrails/Handrails West Elevation

Dome With Bridging Metal On Batten Strips

Excavation 1.jpg

The Finished Dome

LOOK AHEAD SCHEDULE

Click on document icon below to review the detailed Look Ahead Schedule.