THIS WEEK'S ACCOMPLISHMENT

    Cornice Stone Removal East Elevation Completed
    Guardrails/Handrails Ready For Installation
    Batten Bridge Metal Installation Has Begun
    Capital Fire & Safety Onsite For Layout
Excavation 1.jpg

Gable Cornice Stone Left In Place

NEXT WEEK'S ACTIVITIES

    Guardrails/Handrails Installation Main Entrance North Side
    Remaining Rufinox Shingles To Arrive At Empire
    Shingle Installation Will Begin
    Soldering At Dome Continues
    Capital Fire & Safety Installation Begins
Excavation 1.jpg

Severely Damaged #4 Cornice Stone

Excavation 1.jpg

Damaged Stone Safely Removed