Weekly Project Update
FUMC

Pat Tims
THIS WEEK'S ACCOMPLISHMENT
- Guardrails/Handrails Installed South Elevation Main Entrance
- Dome Completion/Cleaning To Follow
- East Elevation Stone Production Begins
- Fire Alarm System Work Resumes
- Red River Restoration Working On Dutchman Repairs North Sanctuary Windows
-

Flashing Closure Metal On Dome
NEXT WEEK'S ACTIVITIES
- Stone Production Continues
- Stained Glass Sanctuary Window Restoration In Process; Two Windows Scheduled For 10/10/2024 Installation
- Presidio Metalworks Continues On Guardrails/Handrails West Elevation Lower Level
- Red River Restoration Fabricating Trim For Sanctuary Windows
- Fire Alarm Installation Completion

- Ash Masonry Explore Anchor Bolt Sectional Loss In Stones
New Guardrails/Handrails South Elevation Main Entrance

New Beginnings
LOOK AHEAD SCHEDULE
Click on document icon below to review the detailed Look Ahead Schedule.