THIS WEEK'S ACCOMPLISHMENT
- Removed Bird Deterrent System
- Removed Finial Stones 1A,1B, 1C, Cornice Stones 1, 2, & Cornice 4 Stones West Elevation North Gable
- ARC Abatement Finished W-401,W-4-2,W-403, W-404, W-405
- Empire Roofing Working On The Dome Punch List
- Red River Sealed & Painted Windows N-402, N-403 For Architect's Approval
- Stanton Studios Finishing N-404, N-405, N-406 For Installation On 11/14

Rigging For Stone Removal West Elevation North Gable
NEXT WEEK'S ACTIVITIES
- Dome Punch List Repairs Completed
- Stanton Studios Installs N-404, N-405, N-406
- Stanton Studios Protective Glazing Frame Installation To Insure The Correct Fit/Production Of Frames/Tempered Glass Ordered
- Capital Fire Alarm Punch Walk With OAC Tuesday 11/12
- Pyramid Stone Cor #4 Stone Production Of 8-10 Stones

- Repairs & Painting From Fire Alarm Installation
Stone Removal West Elevation North Gable

Balcony Window N-402