THIS WEEK'S ACCOMPLISHMENT

    Removed Bird Deterrent System
    Removed Finial Stones 1A,1B, 1C, Cornice Stones 1, 2, & Cornice 4 Stones West Elevation North Gable
    ARC Abatement Finished W-401,W-4-2,W-403, W-404, W-405
    Empire Roofing Working On The Dome Punch List
    Red River Sealed & Painted Windows N-402, N-403 For Architect's Approval
    Stanton Studios Finishing N-404, N-405, N-406 For Installation On 11/14
Excavation 1.jpg

Rigging For Stone Removal West Elevation North Gable

NEXT WEEK'S ACTIVITIES

    Dome Punch List Repairs Completed
    Stanton Studios Installs N-404, N-405, N-406
    Stanton Studios Protective Glazing Frame Installation To Insure The Correct Fit/Production Of Frames/Tempered Glass Ordered
    Capital Fire Alarm Punch Walk With OAC Tuesday 11/12
    Pyramid Stone Cor #4 Stone Production Of 8-10 Stones
Excavation 1.jpg
    Repairs & Painting From Fire Alarm Installation

Stone Removal West Elevation North Gable

Excavation 1.jpg

Balcony Window N-402