Weekly Project Update
FUMC

Pat Tims
THIS WEEK'S ACCOMPLISHMENT
- Protective Glazing Installation Completed N-402, N-405
- Ash Masonry Set E&D 1's East & West Elevations, Set 3 Cor-4 Stones
- Capital Fire Alarm Completed Installation Of Protective Cages In Wesley Hall
- Red River Restoration Removed S-207 For Restoration
- Stanton Studios 70% Complete On leading Family Room Stained Glass Windows
- Capital Fire Alarm Owners Training & Walk Through Inspection Scheduled For Three Pm Thursday 2-13

S-207 Removal For Restoration
NEXT WEEK'S ACTIVITIES
- Protective Glass Installation Continues On North Elevation
- Red River Restoration Installation Of N-406 Sash
- Pyramid Stone Delivery E&D 5, 5OH Stones
- Pyramid Stone Molds For Cor 7, 7OH Stones Completed & In Production
- Ash Masonry Setting E&D 5, 5OH Stones

- Capital Fire Alarm Owners Training & Walk Through Thursday 2-13 At Three PM
N-402 Completed

N-405 Completed
LOOK AHEAD SCHEDULE
Click on document icon below to review the detailed Look Ahead Schedule.