THIS WEEK'S ACCOMPLISHMENT
- Completed flatwork
- Completed wall panels
- Pulled service wire from trans-socket to new pole.
- Poured new entryway
- Installed overhead doors
- Set propane tanks

Bollards, rebar, and sleeved pathway in propane pad.
NEXT WEEK'S ACTIVITIES
- Form and pour locker bases
- Feild measure for millwork
- Install exhaust fan curbs
- skim coat, prime and 1st coat girl's side of the building
- Above ceiling inspection on girl's side

- Install drywall on ceilings on the girl's side
Set new propane tanks.

Poured new entryway to the project.
LOOK AHEAD SCHEDULE