Weekly Project Update

FISD Field House

Placeholder

Nathan Stanford

THIS WEEK'S ACCOMPLISHMENT

    Completed flatwork
    Completed wall panels
    Pulled service wire from trans-socket to new pole.
    Poured new entryway
    Installed overhead doors
    Set propane tanks
Excavation 1.jpg

Bollards, rebar, and sleeved pathway in propane pad.

NEXT WEEK'S ACTIVITIES

    Form and pour locker bases
    Feild measure for millwork
    Install exhaust fan curbs
    skim coat, prime and 1st coat girl's side of the building
    Above ceiling inspection on girl's side
Excavation 1.jpg
    Install drywall on ceilings on the girl's side

Set new propane tanks.

Excavation 1.jpg

Poured new entryway to the project.

LOOK AHEAD SCHEDULE

Click on document icon below to review the detailed Look Ahead Schedule.