THIS WEEK'S ACCOMPLISHMENT
- BEGAN SHEATHING
- COMPLETED NONLINER DUCT INSTALL
- BEGAN INTERIOR FRAMING
- COMPLETED ELECTRICAL HOMERUNS IN CEILING
- BEGAN OVERHEAD PLUMBING ROUGH
- COMPLETED EXTERIOR FRAMING

BEGAN SHEATHING
NEXT WEEK'S ACTIVITIES
- CONT INTERIOR FRAMING
- CONT EXTERIOR SHEATHING
- BEGAN EXTERIOR ELECTRICAL ROUGH
- CONT OVERHEAD PLUMBING ROUGH
- INSTALL TEMP LIGHTING

-
BEGAN INTERIOR FRAMING

COMPLETED WEST WALL SHEATHING