THIS WEEK'S ACCOMPLISHMENT

    COMPLETED METAL WALL PANEL SYSTEM
    INSTALLED EXTERIOR SERVICE
    BEGAN TROPHY SHELF INSTALL
    CONTINUED TAPE AND FLOAT
    SPRAYED WATER REPELANT ON MASONRY
    COMPLETED ELECTRIC CONNECTIONS TO RTU'S
Excavation 1.jpg

INSTALLED EXTERIOR SERVICE

NEXT WEEK'S ACTIVITIES

    CONTINUE TROPHY SHELF INSTALL
    MAKE CONDENSATE CONNECTIONS TO RTU'S
    INSTALL WOOD BLOCKING
    CONTINUE TAPE AND FLOAT
    INSTALL OVERHEAD DOORS
Excavation 1.jpg

COMPLETED WALL PANEL SYSTEM

Excavation 1.jpg

PEC INSTALLED POLE AND TRANSFORMERS

LOOK AHEAD SCHEDULE

Click on document icon below to review the detailed Look Ahead Schedule.