Weekly Project Update
FISD BAND HALL
Levi Taylor
THIS WEEK'S ACCOMPLISHMENT
- INSTALLED ALL LINER DUCTWORK
- PASSED PLUMBING TOP OUT INSPECTION
- COMPLETED ELECTRIC IN WALL ROUGH
- INSTALLED EXTERIOR HMF
- INSTALLED COPPER INSULATION
-
BEGAN VENEER ON WEST WALL
NEXT WEEK'S ACTIVITIES
- BEGIN SHEETROCK TOP OUT
- CONTINUE NORTH AND EAST WALL VENEER
- BEGIN ZGIRT INSTALL
- WRAP DUCT WORK
- BEGIN TOP OF VENEER FLASHING
-
INSTALLED LINER DUCT
COMPLETED WEST WALL VENEER
LOOK AHEAD SCHEDULE
Click on document icon below to review the detailed Look Ahead Schedule.