THIS WEEK'S ACCOMPLISHMENT
- COMPLETED NORTH WALL METAL STUD FRAMING
- COMPLETED WEST WALL METAL STUD FRAMING
- BEGAN FRAMING SOUTH AND EAST WALLS
- INSTALLED ELECTRICAL HOMERUNS
- INSTALLED DUCT HANGERS
- GROUTED AND POURED BACK COLUMNS

GROUTED AND POURED BACK COLUMNS
NEXT WEEK'S ACTIVITIES
- COMPLETE SOUTH AND EAST WALL FRAMING
- BEGIN EXTERIOR SHEATHING
- INSTALL DUCTWORK
- INSTALL EXTERIOR HOLLOW METAL DOOR FRAMES
- ROUGH IN EXTERIOR ELECTRICAL FIXTURES

-
INSTALLED ELECTRICAL HOMERUNS

COMPLETED WEST AND NORTH SIDES OF METAL STUD FRAMING
LOOK AHEAD SCHEDULE