Weekly Project Update

FISD BAND HALL

Placeholder

Levi Taylor

THIS WEEK'S ACCOMPLISHMENT

    COMPLETED NORTH WALL METAL STUD FRAMING
    COMPLETED WEST WALL METAL STUD FRAMING
    BEGAN FRAMING SOUTH AND EAST WALLS
    INSTALLED ELECTRICAL HOMERUNS
    INSTALLED DUCT HANGERS
    GROUTED AND POURED BACK COLUMNS
Excavation 1.jpg

GROUTED AND POURED BACK COLUMNS

NEXT WEEK'S ACTIVITIES

    COMPLETE SOUTH AND EAST WALL FRAMING
    BEGIN EXTERIOR SHEATHING
    INSTALL DUCTWORK
    INSTALL EXTERIOR HOLLOW METAL DOOR FRAMES
    ROUGH IN EXTERIOR ELECTRICAL FIXTURES
Excavation 1.jpg

INSTALLED ELECTRICAL HOMERUNS

Excavation 1.jpg

COMPLETED WEST AND NORTH SIDES OF METAL STUD FRAMING

LOOK AHEAD SCHEDULE

Click on document icon below to review the detailed Look Ahead Schedule.