First United Methodist Church - EXTERIOR WINDOW RENOVATIONS

Placeholder

Pat Tims

THIS WEEK'S ACCOMPLISHMENT

    Architect Approves Metal Shingle Mockup
    Remaining COR #17 Dutchman, E&D #2, Single COR #17 In Production
    Completed Interior Attic Masonry Tuck Point
    Completed Grouting On Installed Cor #17 Dutchman
    Continued Metal Flashing At Dome Base
    Continued Installation Of Standing Seam Panels At Dome
Excavation 1.jpg

Completed Tuck Point In Attic

NEXT WEEK'S ACTIVITIES

    Remaining COR #17 Dutchman, E&D #2 & Full COR #17 Stone Delivery 5/15/24
    Install Skylight Glass by Red River Construction
    Install Exterior Window Trim At East Elevation Lower Windows
    Continue Sheet Metal Flashing At Base Of Dome
    Continue Standing Seam Installation At Dome
Excavation 1.jpg
    Start E&D #2 Replacement AT South& West Elevations

Reassembled Stain Glass At Stanton Studios

Excavation 1.jpg

Standing Seam Panel Installation At Dome