Weekly Project Update
First United Methodist Church - EXTERIOR WINDOW RENOVATIONS

Pat Tims
THIS WEEK'S ACCOMPLISHMENT
- Architect Approves Metal Shingle Mockup
- Remaining COR #17 Dutchman, E&D #2, Single COR #17 In Production
- Completed Interior Attic Masonry Tuck Point
- Completed Grouting On Installed Cor #17 Dutchman
- Continued Metal Flashing At Dome Base
- Continued Installation Of Standing Seam Panels At Dome

Completed Tuck Point In Attic
NEXT WEEK'S ACTIVITIES
- Remaining COR #17 Dutchman, E&D #2 & Full COR #17 Stone Delivery 5/15/24
- Install Skylight Glass by Red River Construction
- Install Exterior Window Trim At East Elevation Lower Windows
- Continue Sheet Metal Flashing At Base Of Dome
- Continue Standing Seam Installation At Dome

- Start E&D #2 Replacement AT South& West Elevations
Reassembled Stain Glass At Stanton Studios

Standing Seam Panel Installation At Dome
LOOK AHEAD SCHEDULE
Click on document icon below to review the detailed Look Ahead Schedule.
bottom of page