THIS WEEK'S ACCOMPLISHMENT

    Insulation and plywood completed at Annex
    New electrical panel set and installing at Annex
    New electrical panel set and installing at Nursing building
    Final Paint completed at Nursing
    Ductwork installing at Nursing
    DI system delivered to site
Excavation 1.jpg

Final paint completed at Nursing Building

NEXT WEEK'S ACTIVITIES

    Start installing fans and curbs at Nursing Building
    Finish electrical panel install at Nursing Building
    Finish electrical panel install at Annex Building
    Start installing DI system at Nursing Building
Excavation 1.jpg

Ductwork installing for vent fans at Nursing Building

Excavation 1.jpg

Insulation and plywood install completed at Annex Building