Weekly Project Update
CTC Small Capitol Projects
THIS WEEK'S ACCOMPLISHMENT
- Insulation and plywood completed at Annex
- New electrical panel set and installing at Annex
- New electrical panel set and installing at Nursing building
- Final Paint completed at Nursing
- Ductwork installing at Nursing
- DI system delivered to site

Final paint completed at Nursing Building
NEXT WEEK'S ACTIVITIES
- Start installing fans and curbs at Nursing Building
- Finish electrical panel install at Nursing Building
- Finish electrical panel install at Annex Building
- Start installing DI system at Nursing Building
-

-
Ductwork installing for vent fans at Nursing Building

Insulation and plywood install completed at Annex Building
LOOK AHEAD SCHEDULE
Click on document icon below to review the detailed Look Ahead Schedule.