THIS WEEK'S ACCOMPLISHMENT
- Ceiling grid and tile demo complete at Protective services
- Concrete formed and rebar inspected at Protective Services
- Concrete pourback complete at Protective services
- Ceiling grid and tile installed at Nursing Building
- Doors and hardware installed at the nursing building
- DI System installing

Concrete poured back with weld plate at Protective Services
NEXT WEEK'S ACTIVITIES
- Finish installing DI System (Nursing)
- Install HVAC equipment at Protective Services
- Install structural steel at Protective Services
- Make electrical connections to exhaust fans at Nursing Building
-

-
Ceiling grid and tile complete and doors hung at Nursing

Ceiling demo for structural steel install completed
LOOK AHEAD SCHEDULE