Weekly Project Update
Alpha Nu Chapter of Sigma Chi Fraternity
THIS WEEK'S ACCOMPLISHMENT
- PAINT INTERIOR DOORS 1st, 2nd & 4th FLOORs
- CABINET AND COUNTERTOP INSTALLATION
- INSTALLED LVT FLOORING AT 2ND & 4TH FLOORS
- COMPLETE CERAMINC TILES AT 2ND, 3rd & 4TH FLOOR
- PLUMBING TRIM OUTS OF SHOWERS, FAUCETS AND TIOLETS 2nd & 4th FLOOR
- COA UTILTIY INSPECTIONS OF 8” OF MAIN FOR FIRE SUPPRESSION SYSTEM
INTERIOR ELEVATIONS
NEXT WEEK'S ACTIVITIES
- START UTILITY WORK FROM VAULT TO STREET
- REWORK VAULT CONDUIT TO STREET
- INSTALL DOORS AND HARDWARE AT 2ND & 4TH FLOORS.
- POINT UP AND PUNCH TILE WORK ALL FLOORS
- DOOR FRONTS AND HARDWARE INSTALL OF CABINETS
- CLOSET SHELVING INSTALLS
CHAPTER HOUSE AND DORM
GOOD MORNING SIGMA CHI
LOOK AHEAD SCHEDULE
Click on document icon below to review the detailed Look Ahead Schedule.